Subject: [CPEO-MEF] Hanford (WA) Waste Treatment Plant
 
Hanford Waste Treatment Plant: Contractor and DOE Management Problems Have Led to Higher Costs, Construction Delays, and Safety Concerns GAO-06-602T April 6, 2006 (28 pages)


The Waste Treatment Plant Project at the Department of Energy's (DOE) Hanford site in southeastern Washington state is a massive effort to stabilize and prepare for disposal 55 million gallons of radioactive and hazardous wastes currently held in underground tanks. In 2000, DOE awarded an 11-year, $4.3 billion contract project to Bechtel National, Inc. (Bechtel) to design and construct the plant. Since then, numerous problems and changes have occurred that will significantly increase the project's final cost and completion date. This testimony discusses (1) how and why the project's cost and schedule have changed since 2000; (2) the status of DOE and Bechtel efforts to address these problems and improve project management; and (3) our observations on issues that need to be addressed in going forward. It is based on previous GAO reports and ongoing work.


...

For the complete summary and links to the entire testimony, see
http://www.gao.gov/docdblite/details.php?rptno=GAO-06-602T

--
Lenny Siegel
Director, Center for Public Environmental Oversight
c/o PSC, 278-A Hope St., Mountain View, CA 94041
Voice: 650/961-8918 or 650/969-1545
Fax: 650/961-8918
http://www.cpeo.org

_______________________________________________
Military mailing list
Military@list.cpeo.org
http://www.cpeo.org/mailman/listinfo/military

  Prev by Date: [CPEO-MEF] More about planned Nevada explosion
Next by Date: [CPEO-MEF] San Diego (CA) airports
  Prev by Thread: [CPEO-MEF] More about planned Nevada explosion
Next by Thread: [CPEO-MEF] "Divine Strake" is delayed; action at Nevada Test Site still on for May 28th

CPEO Home
CPEO Lists
Author Index
Date Index
Thread Index